Reference Project - Offshore Wind
Platforms
Conceptual Design of Self Erecting High Voltage Substation
German North Sea
Project Facts
Client
Alstom Grid GmbH
Project Location
North Sea, Germany
Year
01/2011 – 03/2012
IMPaC’s Scope
Conceptual Design
Study
Project Characteristics
Conceptual design of the Offshore High Voltage Substation for wind park Gode Wind II. The wind park is located in the North Sea in approx. 30 m water depth. The design can be used for construction/installation tender purposes.
Study for comparison of concepts for offshore substations - jacket-topside versus self-erecting platform - regarding fabrication, load-out, transport, installation, time and costs.