Reference Project – Oil & Gas
Afam Gas Receiving Facilities
Nigeria
Project Facts
Client
The Shell Petroleum Development Company of Nigeria
Project Location
Niger Delta (Eastern Region)
Investment
10 million USD
IMPaC's Services
12,000 hours
Dates
Kick-off in March 2005
First air freight on August 29, 2005
Mechanical completion on December 5, 2005
First gas delivered on December 15, 2005, as planned
IMPaC's Scope
Project management
Review/amendment of Shell FEED
Basic & detailed design 'fit for air freighting'
Procurement assistance
Site support
Commissioning & start-up assistance
Project Characteristics
The Nigerian Government requested expansion, rehabilitation and improved operation of the Afam Power Plant (APP). The objective of the Gas Receiving Facilities (GRF) Project was an early increase in power output from the refurbished APP V by supplying gas to the turbine driven generators and the elimination of problems with high levels of hydrocarbon condensates.
The facilities include 2 inlet HP separators, water bath heater for optional superheating, 2 filters in series for solid removal (> 5 microns), condensate storage tank (30 m³), open drain system incl. coalescer for oil removal, flare stack with integrated KO-drum, truck loading facility for condensate export.
For the Afam GRF Greenfield fast track project IMPaC provided integrated project development expertise and has significantly contributed to the first gas delivery in December 2005, as planned.